Illustrative image – not actual.Three engineering companies – Bechtel,
GE and Enron Engineering – associated with the Dabhol Power Project have
decided to withdraw from phase II of the project.
This follows the inability of DPC to
make long overdue payments by the stipulated date of 16 June 2001.
Work on the 1444 MW phase II has come
to a standstill following the withdrawal of these construction companies from
the project.
Meanwhile, phase I (740 MW) of the
project is fully operational although the Maharashtra State Electricity Board
has stopped buying power from the DPC.