BCPL Railway Infrastructure executes electrification of Nimtita-New Farakka sectionIllustrative image – not actual.
BCPL Railway Infrastructure has exclusively executed electrification project in Nimtita-New Farakka section of West Bengal. 
 
The company has completed the work of design, supply, erection, testing & commissioning of 25kV, 50 Hz, single phase, ac electrification works including OHE & TSS as composite electrical work in Azimgunj (including), Nalhati (excluding) & Azimganj-New Farakka/ Toldanga (excluding) section, Group-188A & -189 including Sagardighi Thermal Power Station & Sonar Bangla Cement Siding in Azimgunj-New Farakka Section of Howrah & Malda Division of the Eastern Railway under RE Danapur. 
 
The total distance of the project was 79 RKM/152 TKM. The total value of the project was around Rs 314 million. 
 
The company has conducted a trial run at 100 km per hour on the newly electrified Nimtita-New Farakka section, which has concluded 100 percent electrification of the Eastern Railway.

 