Batot Mini Hydel Power plant by June 2008Illustrative image – not actual.

The 3.5 MW mini hydel power plant of Batot Hydro Power, a special purpose vehicle floated by Weizmann Group, is expected to go commercial by June 2008. According to company officials so far, 30 per cent of the tunneling work of the project has been completed.

The Rs.22 crore project, coming up in Himachal Pradesh will involve installation of two units of 1.75 MW each. Kirloskar Brothers is the machinery supplier, Shanti Flats Construction, Himachal Pradesh is the civil contractor and Trust House Constructions is executing the tunnel works.

Related Links:
Project profile

prjexcl