Illustrative image – not actual.The Barapullah Nullah project in Delhi is unlikely to be inaugurated on 23 September 2010.
The PWD is yet to complete some work on carpeting of the road as the work was affected due to rain. Hotmix worth nearly Rs 20 lakh has been wasted due to rain in the last few days. The PWD is now planning to use blowers to dry the road surface. It may ask labourers to work under tarpaulin cover to meet deadline. It needs least six to eight hours of work to carpet around 300-mtrs stretch where work is still needed.
The elevated road over Barapullah Nullah is a critical link which is to be used by athletes and games delegates to travel from the Village to Jawaharlal Nehru Stadium. The Rs 550-crore elevated road over the nullah was originally scheduled to be completed in June 2010.
Related Links:
Project profile
Addendum:
Sheila Dikshit, Chief Minister of Delhi, on 9 December 2010 inaugurated the elevated road over Barapullah Nullah in Delhi.