Illustrative image – not actual.Phase-II of the Barapullah elevated corridor undertaken by Public Works Department (PWD) Delhi, may miss the deadline of March 2015.
So far, only 20 per cent of work on the project has been completed and the project has been stuck for the past six months. The project, estimated to cost Rs 530 crore, was conceptualised before the Commonwealth Games which were held in Delhi, in the year 2010.
The Barapullah elevated corridor project is proposed to connect South Delhi with East Delhi through the Barapulla flyover and is being implemented in three phases.
However, Phase-I, stretching from Sarai Kale Khan to Jawaharlal Nehru Stadium was completed in December 2010.
Phase-II of the project involves extension of the stretch upto INA Market, while Phase-III will extend the elevated road to Mayur Vihar.
Work on Phase-II of the project had commenced in the year 2012.
Moreover, PWD will also construct cycle tracks and footpath along the Phase-III stretch of the elevated corridor. The road will have four lanes and loops.
The project can be further delayed for want of permission from the Railways to cross a railway line at Kotla Mubarakpur village.