Bannari Amman Sugars invests in capacity expansionIllustrative image – not actual.

Bannari Amman Sugars is expanding the crushing capacity at its Alathukombai plant in Tamil Nadu by 1,500 tccpd and setting up a 20 MW co-generation.

 

The crushing capacity of the Tamil Nadu facility is being increased from 2,500 tonnes of canes crushed per day (tccpd) to 4,000 tccpd. This project is expected to be ready by March 2001.

 

The co-generation plant, using baggasse as fuel, is expected to be ready by June 2002. The estimated cost of this project is Rs.75 crore would be funded as under:

 

Source

Rs.crore

Internal Accruals

20

Financial Institutions

35

Sugar Development Fund

20

Total

75

 

The company has recently completed an expansion project at its Alaganchi plant in Karnataka, where the crushing capacity has been raised from 2,500 tccpd to 5,000 tccpd. A co-generation plant was also set up and the same has already been synchronized to the grid of the Karnataka Power Transmission Corporation.