Illustrative image – not actual.Bannari Amman Sugars is expanding the crushing capacity at its Alathukombai plant in Tamil Nadu by 1,500 tccpd and setting up a 20 MW co-generation.
The crushing capacity of the Tamil
Nadu facility is being increased from 2,500 tonnes of canes crushed per day
(tccpd) to 4,000 tccpd. This project is expected to be ready by March 2001.
The co-generation plant, using
baggasse as fuel, is expected to be ready by June 2002. The estimated cost of
this project is Rs.75 crore would be funded as under:
|
Source |
Rs.crore |
|
Internal Accruals |
20 |
|
Financial Institutions |
35 |
Sugar Development Fund
|
20 |
|
Total |
75 |
The company has recently completed
an expansion project at its Alaganchi plant in Karnataka, where the crushing
capacity has been raised from 2,500 tccpd to 5,000 tccpd. A co-generation plant
was also set up and the same has already been synchronized to the grid of the
Karnataka Power Transmission Corporation.