Illustrative image – not actual.Bangalore Metro Corporation is planning to complete the underground tunnelling work on the East-West and North-South Corridors of Bangalore metro rail project by December 2014.
Currently, tunnelling work is going on between Mantri Mall in Malleswaram and Majestic. Tunnelling under the railway lines between Majestic and City Railway station is expected to start in November 2013.
The tunnelling work of East-West corridor is 85 per cent completed and a tunnel length of 4,666 mtr has been completed out of the targeted 5,130 mtr. The North-South corridor is 39 per cent completed, and the tunnel length completed is 1,050 mtr out of 5,062 mtr.
Further, the National College metro corridor will be completed by March 2014 and services between Byappanahalli and Mysore Road will be run by 2014.