Illustrative image – not actual.The Bangalore-Hassan railway line of the South Western Railway is facing further delay due to various issues.
The Karnataka government is yet to hand over 62 acre required for the project, and at least Rs 600 crore to complete the work.
The project, estimated to cost Rs 809 crore, envisages the construction of 166 km BG line between Hassan and Bangalore, passing through the temple town of Shravanabelagola in Mandya district.
The state government will release its share of funds for the project when the Railway Board does. It has initiated the process to acquire the required land but is delayed due to certain litigations. Because of this, the state government and the Railways are planning to realign the line.