Bangalore Airport: Work might begin in March 2005Illustrative image – not actual.

The Karnataka government, on 20 January 2005, signed the two crucial agreements enabling physical work on the Devanahalli international airport project to commence shortly.

The two agreements in question are the land lease agreement for 4,050 acres and the state support agreement for a Rs.350 crore soft loan with the holding company Bangalore International Airport Ltd.

With these signed and two relatively smaller pacts to follow, it would be a matter of 20-30 days before the company could reach the last milestone, the financial agreement, with lead creditor ICICI Bank.

The project is targeted for completion by end-2007 or 33 months from starting the works.

The project was originally meant to be completed by the middle of 2005 but the mother concession agreement alone took over two years before it was approved and signed by the Centre in July 2004.

According to BIAL CEO, Mr Albert Brunner, the CNS/ATM (communication, navigation systems and air traffic management) agreement with AAI and the O&MS (operations and maintenance services) agreement with consortium partner Unique Zurich airport were on the verge of being signed. According to him, He expected to tie up the finances by the end of February this year and begin airport works by mid-March.

The Rs.1,334 crore project will have 25 per cent as equity from the Siemens-L&T-Unique Zurich Airport combine and the AAI-KSIIDC duo; 25 per cent as repayable State loan; and the rest as debt for which the company would now begin negotiations with ICICI Bank.

The project, conceived in 1994, was awarded in 1999 to the consortium of Siemens, L&T and Unique Zurich Airport as majority private sector partners who will hold equity in the ratio of 40:17:17. KSIIDC and AAI will each hold 13 per cent equity in the venture.