Illustrative image – not actual.According to the Principal Secretary, Infrastructure
Development of the state government, Mr S Krishna Kumar, the financial closure
of the Bangalore international airport project is likely to be delayed by a few
months. Mr Kumar expected financial closure to be achieved in November – December
2002, while operations would commence in June 2005.
Earlier, the project was expected to achieve
financial closure by September 2002.
It may be mentioned that the concession agreement,
which is required for achieving financial closure, has yet to be signed by the Centre,
the state government and the Siemens led consortium. However, the signing of
this agreement itself is awaiting a couple of amendments to the Airports
Authority of India Act, 1994.
Another pending issue that is delaying the financial
closure is the state support agreement, which has to be signed by the state government
and the Airport Authority of India. The draft for this agreement is expected to
be finalised in a few days.
The airport project is estimated to cost US$ 200
million and an additional US$ 30 million as provision for a 7.5 per cent
provision for escalation and an equal amount for contingency.