Bangalore airport project's financial closure likely to be delayedIllustrative image – not actual.

According to the Principal Secretary, Infrastructure Development of the state government, Mr S Krishna Kumar, the financial closure of the Bangalore international airport project is likely to be delayed by a few months. Mr Kumar expected financial closure to be achieved in November – December 2002, while operations would commence in June 2005.

 

Earlier, the project was expected to achieve financial closure by September 2002.

 

It may be mentioned that the concession agreement, which is required for achieving financial closure, has yet to be signed by the Centre, the state government and the Siemens led consortium. However, the signing of this agreement itself is awaiting a couple of amendments to the Airports Authority of India Act, 1994.

 

Another pending issue that is delaying the financial closure is the state support agreement, which has to be signed by the state government and the Airport Authority of India. The draft for this agreement is expected to be finalised in a few days.

 

The airport project is estimated to cost US$ 200 million and an additional US$ 30 million as provision for a 7.5 per cent provision for escalation and an equal amount for contingency.