Illustrative image – not actual.The Bangalore international airport project is headed to achieve financial closure by the end of June 2005, it is learnt.
On 23 June 2005, State Bank of India gave guarantee for the Rs.350 crore long-term state support (contingency loan) to Bangalore International Airport Co Ltd. ICICI Bank, the leader of the lending consortium, is expected to formally declare the financial closure of the Rs.1,334 crore airport project, by end of June 2005.
Civil works at the site are expected to commence soon after the financial closure. BIACL would start raising the boundary wall, construct staff quarters and set up its field office, to begin with. In April 2005, BIACL began preliminary ground preparation work.