Bangalore airport: Financial closure likely by OctoberIllustrative image – not actual.

The consortium of Siemens Project Ventures Gmbh, Unique Zurich Airport AG and Larsen & Toubro (L&T), is expected to complete all formalities of finalising the development of the Bangalore international airport project shortly and achieve financial closure of the project by October 2002.

 

The consortium aims to achieve financial closure with a debt-equity ratio of 70:30. Construction is scheduled to start in October 2002 and commercial operations may start by mid-2005.

 

While Siemens Project Ventures holds 40 per cent in the project, Unique Zurich Airport and L&T have 17 per cent stake each. Karnataka State Industrial Investment & Development Corporation (KSIIDC) and Airports Authority of India will share the remaining stake equally. Siemens Project Ventures would invest around $24 million in the project, which would have an equity base of about $60 million. Unique Zurich Airport would operate the new international airport.

 

The nodal agency, KSIIDC, has raised a loan of Rs.150 crore from HUDCO for acquiring around 4,300 acres of government and private land at Devanahalli, 30 km from Bangalore.

 

All the support infrastructure is being taken up simultaneously to speed up the project. A 23 km toll expressway from Nagavara to the airport site, would be developed by Malaysian firm Actacorp Holding Bhd on a 27-year concession period. Another six-lane highway segment up to Bangalore is coming up as part of the North-South highway corridor project. A direct shuttle rail service from Yelakanka to Devanahalli, is also being taken up. Work on establishing power and water supplies is also underway.

 

A master plan for the airport also envisages software and hardware parks, resorts, a five-star hotel and a water park, among other facilities.