Balrampur Chini to set up Rs.120 crore integrated sugar complexIllustrative image – not actual.

Balrampur Chini Mills is setting up a fully-automated integrated sugar complex at Barabanki in Uttar Pradesh.

 

The project cost is estimated at Rs.120 crore, which would be brought in through debt and internal accruals. The project would have a debt equity ratio of 1:1 with minor changes.

 

The complex would have a sugar factory of 4,000 tonnes of cane crushed per day, a 60 kilolitre per day ethanol plant, a 16 MW co-generation plant and a bio-compost manufacturing plant. This project would be commissioned in December 2003.

 

The company is also setting up a 19.55 MW power plant at Balrampur, also in Uttar Pradesh, which would be commissioned in December 2002.

 

The bagasse and the molasses from the sugar factory would be consumed by the power plants and ethanol plant.