Illustrative image – not actual.India’s largest sugar-producing
company, Balrampur Chini Mills (BCML), is planning to set up an 18 MW
bagasse-based power plant near its sugar mill at Balrampur in Uttar Pradesh.
BCML has applied to the Uttar Pradesh Power
Regulatory Commission for permission to set up the plant. Subsequently,
clearance from Uttar Pradesh Power Corporation Ltd (UPPCL) would also have to
be sought.
The 18 MW power project is expected to
cost Rs.50 crore. Out of the 18 MW, power worth 3 MW would be consumed by the
company while the rest would be sold to the State grid.
This project, which was first proposed
in January 2001, has now undergone changes. As per the original plans, a 15 MW
power plant costing Rs.60 crore was to be set up.
BCML has appointed Chennai-based Avant
Garde Engineering & Consultants as project consultants.
BCML has three units located at
Balrampur, Babhnan and Tulsipur, having a total capacity of 25,000 tccpd. The
respective capacities of these units are 6,000 tccpd, 8,000 tccpd and 11,000
tccpd. The company’s aggregate capacity till the end of 2000 stood at 20,500
tccpd.