Illustrative image – not actual.Bharat Aluminium Co’s cold rolling mill project, which was
expected to be completed by March 2000, is likely to get delayed by another
year. The delay has also led to an
escalation in cost from the original estimate of Rs.157 crore to Rs.183 crore.
In this report submitted to the Ministry of Mines, BALCO has
cited lapses on part of the EPC contractor, equipment supplier, and the civil
works contractor, as reasons for the delay.
The project, cleared by the Public Investment Board in 1997,
envisaged the setting up of an additional 36,400 tonnes per annum of
cold-rolled products. The project, when commissioned, would result in an
increase in Balco’s cold rolled products capacity from the present 40,000 tpa
to over 76,000 tpa.
The delay in this project may also have a deterrent impact
on the government’s plan of offloading 51 per cent of its stake in Balco, in
favour of strategic investors, by the end of 2000-01.