Bakreswar thermal project: BHEL-Itochu bags orderIllustrative image – not actual.

The Bhel-Itochu combine has bagged the Rs.1,400 crore-plus main plant package order of the Bakreswar thermal power project (Stage II of 2x210 MW) in West Bengal. The project promoter, West Bengal Power Development Corporation, took this decision on 17 September 2004.

The Bhel-Itochu consortium had bagged the EPC contract for the 630 MW Stage I of the same project in the early 1990s.

Actual placement of orders for the second stage will start once the go-ahead is received from Japanese Bank of International Co-operation.

The project would be financed through soft loans from JBIC that would make up 85 per cent of the total project cost. WBPDCL will bring in the remaining 15 per cent as equity.