Illustrative image – not actual.The Bakreswar Thermal Power Project, being implemented by West Bengal Power Development Corporation Ltd, was dedicated to the nation on 11 February 2001.
The power station of 630 MW has three units of 210 MW each. The first two
units have already been commissioned in April 1999 and May 2000, respectively.
The third unit that has been commissioned is expected to be synchronized
to the grid on 20 February 2001.
The total amount spent on the project up to January 2001 was Rs.2,573
crore.
The project has been funded through Japanese Bank of International Co-operation to the extent of 85 per cent and 15 per cent through West Bengal State Plan Fund.