Bakreswar Power Project: BHEL achieves milestone ahead of scheduleIllustrative image – not actual.

On 24 April 2007, Bharat Heavy Electricals achieved a milestone in execution of West Bengal Power Development Corporation's Bakreswar power project in West Bengal with the light up of Unit I (210 MW) boiler, 30 days ahead of schedule.

The erection of the boiler commenced within 144 days from the start of the civil foundations as against schedule of 195 days and key elements of contract like boiler-drum lifting and hydraulic testing were also achieved ahead of schedule.

The main package plant of 3x210 MW power plant had been awarded on a turnkey basis to BHEL-Itochu combine. The project is being funded by OECF of Japan in which BHEL has the major share covering boilers, generators, auciliaries, controls and instrumentation, all balance of plants, civil and construction works.