Illustrative image – not actual.The Government of West Bengal has planned to wind up Bakreswar Power Generation Co, the company implementing the 420 MW Bakreswar power project (stage II) in Birbhum district of West Bengal.
This decision follows Ogden Energy Asia-Pacific’s, one of the project promoters, decision to walk out of the project. Ogden Energy has decided to pull out of the project as after receiving environment and CEA techno-economic clearances in 1996 and 1998 respectively, the project has not made much progress.
Prior to Ogden Energy, two other companies, viz. CMS Energy of Detroit and Entregy Corp of California have walked out of the project. With Ogden dropping out of the project, WBPDCL would be implementing the project alone.
Presently, Ogden Energy together with Development Consultants holds 74 per cent equity in BPGC. The remaining 26 per cent in BPGC is held by West Bengal Power Development Corporation (WBPDCL).
Meanwhile, the 630 MW stage I of the project was been completed and dedicated to the nation on 11 February 2001.