Illustrative image – not actual.Bajaj Hindusthan Ltd (BHL), the sugar producer, has received approval of Uttar Pradesh Power Corp Ltd to relocate its upcoming power projects from Bargarh in Chitrakoot district to Mirchwara in Lalitpur district within the state.
The 1,980 MW power project of BHL-owned Bajaj Power Generation Private Ltd (BPGPL) was stuck by non-availability of adequate water. Under the existing system, the company could have availed of water from the Yamuna only after receiving necessary approvals for construction of a barrage across the local river. This led the company to seek relocation of the project which will now be clubbed with another 1,980 MW project planned at Lalitpur.
For the Lalitpur project, BHL has already completed acquisition of 1,289 acres (out of the total requirement of 1,320 acres) being promoted by a special purpose vehicle, the Lalitpur Power Generation Company. The twin projects would entail investment of Rs 12,000 crore each. The fuel linkage from the coal ministry is awaited. However, BHL plans to import the carbon resource from Indonesia for its entire needs.