Illustrative image – not actual.Bajaj Electricals has managed to bag a new order worth Rs 108.63 crore.
The Engineering & Project Business Unit of the company has secured an order for turnkey construction of transmission lines from Maharashtra State Electricity Transmission Company.
Bajaj Electricals needs to construct a 400 kV D/C line from 400 kV Koradi-II S/Station to 765 kV Koradi-III S/Station, with a total line length of 35 km. It needs to further undertake supply of towers, insulators, earth wire, testing and commissioning of the line on turnkey basis, and more.
The completion period is of 12 months from the date of LoA.