Illustrative image – not actual.The board of directors of the Rashtriya Ispat Nigam (RINL) on 18 July 2011 inaugurated various auxiliary units in Visakhapatnam, Andhra Pradesh.
The units are critical to expansion of the plant capacity to 6.3 million tonne from the present three million tonne. The facilities include coke oven boosting station which boosts CO gas pressure of 500-600 mmWC (milllimeter of water) to 1500 mmWC and caters to the CO gas requirement of all the expansion units. Further, a new gas mixing station installation, wherein three different types of gases will be mixed and homogenised has begun operations. The project has been executed by Instrumentation, Kota, and associates at a cost of around Rs 10 crore.
Further, the chilled water plant – V which has 10 pumps with a capacity of 1,000 tonne refrigerant with incoming temperature of 18 -20 degrees celsius to the condensers and outgoing chilled water has a temperature of 7-8 degrees celsius was also commissioned.
The project was executed by Indian Diary Manufacturing Company, Anand, at a cost of Rs 36 crore. The drying of first Tundish, a prerequisite for commissioning the new steel melt shop has also been operationalised.