Illustrative image – not actual.The Assam State Electricity Board (ASEB) has invited proposals from private sector players for setting up a coal-based power project and a gas-based power project in the State.
The coal-based power project would
have a capacity of 2 x 60 MW. It is to be set up on a build-own-operate (BOO)
basis at Udaipur village, 20 km from Margherita town in Tinsukhia district of
Assam.
The entire power generated from the project would be
purchased at 132 KV Bus of the power station by the ASEB at the agreed tariff.
Coal for the project is to be sourced from the Tipang
colliery B, which is 10 km away from the project site, while the water
requirement of the project would be met from Buridihing river, 7 km from the
project site. The availability of coal, water and limestone has been established.
The management of coal, fuel oil and lime stone would be under the scope of the
project developer.
The last date for submission of requests for
pre-qualification is 19 February 2001.
The gas-based power project
would have a capacity of 90-100 MW. It is to be set up on a BOO basis at Amguri
in Sivasagar district of the State. The site is 7-9 km from the National
Highway No.37 from Jhanji via Dhodor Ali.
The plant would have a configuration of two gas turbines,
two heat recovery steam generators and one steam turbine. Natural gas for the
project would be supplied by Oil India Ltd from Duliajan offtake point and gas
transmission would be done by Assam Gas Company Ltd. The water requirement for the
project would be met from Dikhau river, about 15 km away from the power
station.
The fuel cost, inclusive of the cost of transmission, would
have to be negotiated by the IPP with the fuel supplier/ transporter, with the
concurrence of ASEB.
The entire power generated from the project would be
purchased at 220 KV Bus of the power station by the ASEB at the agreed tariff.
The last date for submission of requests for
pre-qualification is 15 February 2001.