Assam Gas Cracker Project: Rehabilitation plan for displaced families preparedIllustrative image – not actual.

The Dibrugarh district administration of Assam has prepared a draft rehabilitation scheme for relocation of 56 families that would be displaced by the Assam Gas Cracker Project proposed to be set by Reliance Assam Petrochemicals Ltd (RAPL).

 

Besides, plans have also been made for 150 families that are likely to be indirectly affected by the project.

 

The administration is also in the process of handing over project site at Lepetkota to RAPL by 31 December 2000.

 

It may be recalled that the Gas Supply Agreement with Oil India Ltd and RAPL was signed on 19 October 2000.

 

RAPL has expressed confidence of commencing work on 1 January 2001 provided land is handed over by 31 December 2000.

 

The Assam Gas Cracker Project is designed to produce two lakh tonnes of ethylene annually. Of the total natural gas requirement, OIL has agreed to supply 5 million standard cubic metres (mscm) while ONGC has made a similar agreement for 1.35 mscm.

 

RAPL has already begun spadework for the project in the form of conducting environmental impact assessment, evaluation of process knowhow and identifying foreign technology suppliers.

 