Assam Gas Cracker Project may be delayedIllustrative image – not actual.

The Rs.4,300 crore Assam Gas Cracker Project might get further delayed owing to ONGC’s inability to sign a gas supply agreement with the project promoter, Reliance Assam Petrochemicals Ltd.

 

RAPL was to sign two agreements with Oil India Ltd (OIL) and Oil & Natural Gas Corporation (ONGC) for the supply of natural gas required for the 2 lakh tpa ethylene project.  The agreement with OIL was signed on 19 October 2000, for the supply of 5 million metric standard cubic metres per day (mmscmd) out of the total requirement of 6.4 mmscmd. ONGC was to supply the remainder.

 

The Union Minister for Petroleum & Natural Gas, Mr Ram Naik, stated that if the project size is brought down to 1.5 lakh tpa, the gas supply agreement could be signed immediately.

 