Illustrative image – not actual.The Rs.4,300 crore Assam Gas Cracker
Project might get further delayed owing to ONGC’s inability to sign a gas
supply agreement with the project promoter, Reliance Assam Petrochemicals Ltd.
RAPL was to sign two agreements with
Oil India Ltd (OIL) and Oil & Natural Gas Corporation (ONGC) for the supply
of natural gas required for the 2 lakh tpa ethylene project. The agreement with OIL was signed on 19
October 2000, for the supply of 5 million metric standard cubic metres per day
(mmscmd) out of the total requirement of 6.4 mmscmd. ONGC was to supply the
remainder.
The Union Minister for Petroleum &
Natural Gas, Mr Ram Naik, stated that if the project size is brought down to
1.5 lakh tpa, the gas supply agreement could be signed immediately.