Assam gas cracker complex: Financial closure by SeptemberIllustrative image – not actual.

Financial closure for Brahmaputra Cracker & Polymer's Rs.5,460 crore petrochemical plant at Dibrugarh in Assam is expecting financial closure by September 2008.

Brahmaputra Cracker is a joint venture company with GAIL holding a 70 percent stake, and the remaining 30 percent equity shared equally among Oil India, Numaligarh Refinery and the Assam government.

Major construction activities is expected to commence by August-September 2008 and full project completion with a production capacity of 2.80 lakh tpa is scheduled by 2012.