Asia’s biggest surge pool to be ready for lifting Kaleshwaram watersIllustrative image – not actual.

Asia’s biggest surge pool will be filled with waters of Kaleshwaram Lift Irrigation Project and the same water lifted to the Ananthagiri Reservoir in a few days and from there later to the Mallannasagar in Siddipet district.

The surge pool is constructed on hillocks on the outskirts of Thippapur village in Illanthakunta mandal. It measures 92 mtr deep and 56 mtr diameter and can store one TMC ft of water, which will be lifted by using four motors to the Ananthagiri Reservoir.

The water will reach the surge pool from Mid Manair Dam-Sri Raja Rajeshwara reservoir by travelling 3.4 km through gravity canal and 7.6 km through tunnel.

The surge pool, open to the sky, has been constructed in a record time of 13 months at an investment of Rs 2,700 crore.

The four motors in this pool will use 106 MW of power and accordingly a 440 kVA sub-station was constructed at the vicinity of the pool. The pumps will daily lift one tmc feet of water into Ananthagiri Reservoir and from there to the Mallannasagar.

 

← All latest storiesBack to top →