Ashoka Buildcon has received commercial operation date (CoD) for its hybrid annuity mode (HAM) project of the National Highways Authority of India (NHAI) on 13 October 2020.
The project involves four-/six-laning from Ranastalam to Anandapuram (Visakhapatnam), from 634.000 km to 681.000 km section of NH05 (New NH-16) in the state of Andhra Pradesh under NHDP Phase-V (Package II) on HAM.
The project is executed by Ashoka Ranastalam Anadapuram Road, a special purpose vehicle (SPV) and a wholly-owned subsidiary of Ashoka Concessions.
The SPV is eligible for receipt of annuity payments from NHAI within six months from the date of achievement of CoD i.e. six months from 24 September 2020.