Ashoka Buildcon has declared 09 October 2021 as the commercial operation date (CoD) for its hybrid annuity mode (HAM) project of the National Highways Authority of India (NHAI) vide letter issued by Independent Engineer on 11 October 2021 for a road project.
The project involves six-laning of Khairatunda to Barwa Adda Section of NH-2 from 360.300 km to 400.132 km in the state of Jharkhand under NHDP Phase-V on hybrid annuity mode (HAM).
The project is executed by Ashoka Khairatunda Barwa Adda Road, (SPV) a wholly-owned subsidiary of Ashoka Concessions, a subsidiary of the company.
Further to inform that consequent to the declaration of CoD, the SPV is eligible for receipt of annuity payments from NHAI for the operation period of 15 years at the interval of every six months from the date of achievement of CoD.
The company also announces that the said SPV has received a provisional certificate for completion of 36.40 km out of total project highway length of 40.33 km.