Illustrative image – not actual.Ashapura Volclay is expanding its bleaching clay capacity at its Ler unit, in Kachchh district of Gujarat.
Ashapura will expand its clay capacity from 6,000 tonne per month to 10,000 tonne per month.
The clay project is estimated to cost Rs 75 crore. 75 per cent of the project cost will be funded through bank loan and the remaining 25 per cent from internal accruals.
Moktali Engineering Co and Ecoman have been appointed as the machinery suppliers.
As disclosed to ProjectsToday,
• Civil contractor is yet to be finalised
• Financial closure is underway
• The company is awaiting necessary clearances for the project
• Work on the project is expected to commence by December 2014
More Project Info:
Bleaching Clay (Ler) Project - Expansion