Around 75 percent work completed on India-Nepal petroleum pipelineIllustrative image – not actual.
Around 75 percent work has been completed on the petroleum pipeline being jointly constructed by Indian and Nepalese governments. The first transnational pipeline will extend from Motihari in Bihar, India to Amlekhganj in Parsa, Nepal.

From Nepal side, around 70 to 75 percent of laying the pipeline has been completed, while if considered the distance from the Motihari to Amlekhganj around 50 percent of the work is completed.

The Nepal Oil Corporation (NOC) is funding the construction of the pipeline on behalf of the Nepal government. Around 18 km of the pipeline in Nepal has already been laid. Moreover, other activities are underway as per the schedule. Investment wise, India is pumping Rs 3.2 billion for the project, while Nepal is pouring Rs 1.2 billion for the construction of the pipeline.

The pipeline stretches almost 69 km, covering a distance of 32.7 km in Indian territory and 36.2 km in Nepal. It has a capacity of supplying 2,00,000 ltr of fuel on an hourly basis. Also, a fuel pumping facility has been established in Motihari. Both the governments had inked a pact on 24 August 2015 for developing the project.

← All latest storiesBack to top →