The works of the elevated highway at Kazhakkoottam in Kerala is more than half way through and the works is expected to be completed within next eight months.
RDS Constructions is carrying out the work on the project. Around 65 percent of the work on the project has been completed.
The twin two-lane elevated highway is 2.7 km long starting from CSI Mission Hospital in the North and ending at Technopark Phase-III Junction in the South. Each lane of the elevated highway is 10.5 mtr wide.
The major components of the elevated highway are 60 piers and as many pier caps and concrete slabs and two approach ramps of 250 mtr length on both ends.
So far the company has completed installation of all 60 piers. As many as 49 pier caps and 37 concrete slabs have also been completed.
At present, the workers are engaged in the task of shifting two giant gantry cranes that were used to install girders (large iron framework) from this stretch to the second stretch between Kazhakkoottam and CSI Mission Hospital.
The giant equipment will be dismantled and the parts will be transported on trucks. The elevated highway is a key infrastructure project that is expected to resolve traffic woes along the IT corridor of Kazhakkoottam.
Works of the project was affected a few months ago during the second wave of COVID-19 pandemic.