Around 40 percent work completed on bio-pharmaceuticals unit in Bengaluru Illustrative image – not actual.
Anthem Biosciences is setting up a bio-pharmaceuticals, organic nutraceuticals manufacturing unit in Bengaluru district of Karnataka. 
 
The project will come up over 30 acre of land parcel. In 2020, SEIAA, Karnataka accorded environment clearance (EC) for the project. 
 
Work on the project began in September 2020. As per the latest information available with Projects Today, around 40 percent work on the project has been completed. 
 
The project is expected to be completed by October 2023.