Illustrative image – not actual.Areva T&D India has won an order from Lanco Infratech for 765 kV substation that will connect the Anpara 'C' 1200 MW (2X600MW) Thermal power plant being developed by Lanco Infratech at Anpara in Uttar Pradesh to the Northern Grid.
All the major equipments will be produced in Areva T&D's Indian plants. Circuit breakers and disconnectors will be manufactured in the company's new state of art factory at Padappai (Tamil Nadu) while 765 kV instrument transformers will be supplied from its new plant at Hosur (Tamil Nadu). The project will be fully commissioned by April 2010.