Illustrative image – not actual.Areva T&D India has been awarded two electrical Balance of Plant (eBOP) contracts by Essar Projects (India).
The orders worth a total Rs 290 crore are for the 1,200 MW (2x600 MW) thermal power plant at Tori, Jharkhand and 120 MW (4x30 MW) thermal power plant at Paradip, Orissa.
The scope will include supply and installation of eBOP solutions for the power plants for which the company will manufacture and install a 400 kV gas insulated substation and 220 kV air-insulated substation, as well as distribution and power transformers and low voltages switchboards.
Also See:
Areva T&D, Lanco Infra commission 765 kV transformers (10-Feb-11)