ArcelorMittal revises Jharkhand planIllustrative image – not actual.

ArcelorMittal has revised the scope for setting up a 12 million tpa steel plant.

In place of one plant, the company has decided to set up two plants having six million tpa capacity each. One plant is to come up at Petarwar in Bokaro district of Jharkhand while the location for the other plant is undecided.

The company has started acquiring 2,500 acre in Petarwar for the plant. It hopes to acquire 1,000 acre by this December 2010 and the rest by the first few months of 2011. The plant is expected to be built in two phases of three million tpa each.

Related Links:
Project profile

← All latest storiesBack to top →