APSEZ to get more time to execute Vizhinjam port projectIllustrative image – not actual.

The Kerala government is set to give more time to the Adani Ports and Special Economic Zone (APSEZ) to complete construction and start commercial operations on Phase-I of the deep water multi-purpose port at Vizhinjam.

The government agreed with APSEZ’s plea that the project has been delayed due to force majeure events including the pandemic.

Adani Vizhinjam Port (AVPPL), the subsidiary set by APSEZ to implement the project, was contractually mandated to start commercial operations by 3 December 2019 according to the concession agreement signed on 17 August 2015.

The concession pact also allowed a grace period of 270 days to complete the project, comprising first 90 days without damages and the next 180 days with penalty, calculated at the rate of 0.1 percent of the performance security amount for each day of delay, to be paid to the Kerala government.

The 270 days grace period ends on 30 August 2020 after which the state government has the right to terminate the concession agreement.

The 180 days grace period with damages coincided with the nationwide lockdown imposed by the government to slow the spread of Coronavirus, followed by the monsoon period (June to September), when work comes to a standstill.

The change in environment clearance procedures for development of mines to source rocks for construction of breakwater according to the National Green Tribunal order of 13 September 2018 further delayed the project.

The company had also sought revision in the project completion schedule citing the force majeure events.

The Vizhinjam port project is being developed as a container transhipment port with an investment of Rs 5,552 crore.

The project is entitled to receive a viability gap funding (VGF) of Rs 1,635 crore to be shared equally by the Central and state governments to boost its viability, making it the first port project to be offered such a grant.

Of this, Rs 1,227 crore will be given during the construction phase spread over four years and the balance during the operation period spanning 40 years extendable by another 20 years.

Phase-I of the Vizhinjam port will have an 800 mtr long berth capable of handling one million twenty-foot equivalent units (TEUs). The berth length will be extended to two km in three phases with a capacity to load three million TEUs.

 