Approval received for Godavari drinking water supply schemeIllustrative image – not actual.

Union Finance Minister P Chidambaram gave approval for Hyderabad Metropolitan Water Supply & Sewerage Board's Rs.4,000 crore water supply project to bring Godavari river water to the city under Phase I.

The Phase I of Godavari drinking water supply scheme was estimated to cost Rs.3,375 crore, but due to the tremendous increase in cement and steel prices, the project cost will now escalate to Rs.4,000 crore. Tenders had been called and the technical evaluation is underway. The project will be implemented in three phases and the Phase I is expected to be completed by 2011, yielding 120 MGD water.