Appointed date declared for highway project in Uttar PradeshIllustrative image – not actual.

The National Highway Circle, PWD Uttar Pradesh has declared the appointed date for the project being undertaken by GR Yamuna Bridge Highway.

The wholly-owned subsidiary of GR Infraprojects has received a letter in this regard. The completion period is 24 months from the appointed date, and operation period is 15 years from the commercial operation date (COD).

The hybrid annuity mode (HAM) project valued at Rs 737.17 crore entails the construction of a four-lane highway from km 74.700 to km 112.950 (Baranpur Kadipur Ichauli to Rampuriya Awwal) of NH-731A (i/c Yamuna Bridge) in the state.

The appointed date declared is 24 June 2024.