Illustrative image – not actual.Apollo
Tyres has completed the expansion project at its Perambra unit in Kerala. With
this the capacity of the unit has risen to 200 tonnes per day from the earlier
130 tonnes per day.
The
company also expects to complete the expansion project of its subsidiary
Premier Tyres, at Kalamassery (also in Kerala), by June 2003. The capacity of
this unit is being raised from 51 tonnes to 80 tonnes per day.
The cost incurred for both
these projects is around Rs.100 crore. Apollo Tyres is expected to invest
another Rs.100 crore towards the modernization and expansion of the Kalamassery
plant.
Meanwhile,
Apollo Tyres expects its new radial tyre unit at Vadodara in Gujarat, to become
operational by June 2004. The initial production capacity would be 1,000 tyres
per day.
It
may be mentioned that Premier Tyres Ltd (PTL), a sick company, was taken over
by Apollo Tyres in 1995, as per a BIFR agreement. PTL is presently a subsidiary
of Apollo Tyres, with the latter holding 75 per cent equity stake. It is likely
that PTL would be merged with Apollo Tyres after March 2003. Before the takeover,
PTL had a production capacity of around 35 tonnes per day.
Related
News:
Apollo Tyres launches
Perambra expansion project (June 2002)
Foundation stone for
Apollo Tyres’ Vadodara unit laid (November 2002)