APERC wants AP Transco to lower foreign component of project costIllustrative image – not actual.

AP Transco, which has entered into a PPA with BPL for the latter’s 2 x 260 MW power project at Ramagundam, has been asked by Andhra Pradesh Electricity Regulatory Commission (APERC) to look into the possibility of lowering the foreign exchange (forex) component in the equity from 80 per cent to 55 per cent. This was because it was felt that the project cost had escalated due to appreciation of dollar against rupee.

 

The cost of the project has gone up from Rs.2,384.58 crore in 1997 to Rs.2,748.54 crore in February 2001, when the CEA had approved the cost. This revised cost includes a forex component of $326.8 million and a domestic currency component of Rs.1,228.92 crore. It is this forex component that APREC wants lowered.

 

APERC has also asked AP Transco to examine whether it is reasonable to fix a 16 per cent rate of return on the foreign exchange component of the equity. Here APERC wants AP Transco to consider different rates of returns for rupee and foreign currency component because the inflation of dollar was much less compared to that of rupee.

 

AP Transco would be conveying its reply to APREC by 6 July 2001.

← All latest storiesBack to top →