APERC rejects Ramagundam project's PPAIllustrative image – not actual.

On 6 November 2001, the Andhra Pradesh Electricity Regulatory Commission (APERC) rejected the power purchase agreement (PPA) signed between BPL Power Projects (AP) Ltd and Transmission Corporation of Andhra Pradesh Ltd (AP Transco), for BPL's 520 MW power project in Andhra Pradesh.

 

The 2 x 260 MW coal-based power project was to come up at Ramagundam in Karimnagar district of the state. The PPA was signed between BPL Power and AP Transco on 29 January 1999.

 

APERC stated that the PPA did not take into consideration fully the interests of the consumers in the state. The Commission had objected to the issues of plant load factor (PLF) and high foreign exchange component in the project cost.

 

APERC has stated that the threshold PLF for fixed cost recovery should be 80 per cent instead of the original 68 per cent.  It also stated that the incentive for supply of power above the threshold PLF should be based on actual generation and not on deemed generation.

 

The Commission also asked the project promoters to reduce the risk of foreign exchange variation and uncertainty to that extent by conforming to the level of foreign currency approved by the Central Electricity Authority (CEA). The funding pattern approved by the CEA included a foreign currency component of around $326.8 million and a domestic currency component of Rs.1,228.92 crore. However, the promoters had sought to have a foreign currency component of $480.71 million and a domestic currency component of Rs.559.44 crore.

 

APERC also objected to the fact that AP Transco had not stated how it planned to fulfil the escrow obligation. AP Transco had also not furnished information regarding the escrow cover already given to existing IPPs, the balance escrow capacity available and policy regarding distribution of escrow cover.