Illustrative image – not actual.Andhra Pradesh Electricity Regulatory Commission (APERC) has directed AP Transco to re-negotiate the PPA with BPL Power Projects (AP) Ltd for the latter's 2 x 260 MW power project at Ramagundam in Andhra Pradesh.
APERC had examined the proposal on three counts, viz. demand i.e. need for the project, observance of the power purchase procedures and reasonableness of the indicative tariff from the customer’s point of view. APERC cleared the proposal on the first two counts but not on the third.
Following this the commission has asked AP Transco to re-negotiate the PPA on the following issues:
·
Raising
the threshold limit of plant load factor (PLF) to a reasonable level of about
80 per cent
·
Non-payment
of any incentive on deemed generation above the threshold, i.e. the incentive
would be payable only on actual generation above the threshold limit of PLF
·
The
feasibility of converting BPL’s dollar contribution in the equity into Indian
rupees as on the commercial date of operations for all purposes
·
The
possibility of reducing the interest rate spreads which are very high
AP Transco has been asked to submit a report to APERC by 15 September 2001.