APERC approves modified PPA for BPL's Ramagundam power projectIllustrative image – not actual.

In response to APTransco's proposal, the Andhra Pradesh Electricity Regulatory Commission (APERC) has issued its final orders to approve the power purchase agreement (PPA) for buying power from BPL Power Projects (AP) in Andhra Pradesh. The coal-based power project with a capacity of 2x260 MW would come up at Ramagundam.

The major changes in the PPA, that have been agreed to by BPL and APTransco include:

 

·          Raising threshold plant load factor (PLF) to 80 per cent from 68.493 per cent for fixed cost recovery

·          Incentive-based on actual generation from 80 per cent PLF from 68.493 PLF

·          No incentive for deemed generation

·          Adjustment of interest on monthly ROE payment and non-inclusion of interest in the land cost.

 

According to reports, these modifications would have a direct impact on reducing the power purchase cost from this project to the tune of about Rs.60 crore per annum based on reasonable assumptions.

This is reportedly, the first time an IPP in the country has been cleared with a threshold of 80 per cent PLF for fixed cost recovery and payment of incentives on actual generation beyond the threshold PLF of 80 per cent.

← All latest storiesBack to top →