Apeejay Group is reviving a stalled project which is now facing insolvency proceedings.The project was being developed along with Bharati Shipyard.
In 2007, company had formed a joint venture with Bharati Shipyard now known as Bharati Defence and Infrastructure (BDIL).
Since the JV partner is falling out, Apeejay group has decided to go alone and has even enlarged the scope of the project.
The revised project involves the marine industrial cluster spread over 500 acre to be built at a cost of Rs 2,000 crore.
The maritime cluster under consideration would broadly comprise of core and non-core maritime activities like shipbuilding, ship repair, captive cargo handling facility of 4.8 million tpa, logistics and supporting services among others.
The proposed shipyard is targeted to serve nearly about 40 vessels a year of varying sizes including Panamax, Handymax, defence and other offshore vessels for routine as well as capital repairs.
The land and outfitting facility and the shipyard are planned to be rolled out first, commencing operations from the third year (two years of construction and setup), and stabilising period over five to six years.
The proposed cluster would come up over an area of around 554 acre at Kulpi, about 78 km downstream from Kolkata on the banks of Hoogly river.
The Bengal Shipyard has already acquired 524 acre of land and the balance 30 acre land would only need to be get acquired.