Illustrative image – not actual.The Andhra Pradesh government has indicated that the J Chokkarao Lift Irrigation scheme would be completed within two years. Other projects scheduled for completion at the same time include Tadipudi, Pushkaram, Telugu Ganga, Somasila, Alisagar and Gupta
According to the Minister, the irrigation works worth Rs 38 crore in Tadipudi project were completed. Out of the works of Pushkaram projects costing Rs.209 crore, the canal of 30 km length costing Rs.100 crore was completed. The works of Chokkarao Lift Irrigation project worth Rs.250 crore were completed by end April 2005 and water would be released by end-December 2005.
Around 96 per cent of works of modernisation of KC Canal were completed and the balance works would be completed before July 2005. The Janjhavathi Project would irrigate 5,000 acres of land before the monsoon. For the Polavaram projects, 16 foreign companies have come forward and tenders would be floated soon.
Meanwhile, the Andhra Pradesh Chief Minister, Dr YSR Reddy, would lay foundation to Mylavaram-Pulivendula branch canal and Gandikota Lift Irrigation Project on 23 May 2005 and 24 May 2005, respectively.