Illustrative image – not actual.
The Andhra Pradesh government will have 49 percent equity in the special purpose vehicle (SPV) being set up to carry out the Buckingham Canal project. The majority stake in the SPV will be held by the Centre.
The 49 percent equity was offered in place of land being given by AP and some cash contribution. The project will be carried out to connect Kakinada in East Godavari district with Puducherry over a stretch of 1,080 km.
Inland Waterways Authority of India (IWAI) will execute the project in three phases all along the Coromandel Coast to provide inland waterway transport.
The project is in the final stages of approval. The first phase will commence from Kakinada; the second phase from Vijayawada; and third phase from Ennore.
The total project cost for revival of the freshwater navigation canal from Kakinada to Vijayawada is estimated at Rs 4,000 crore, which also includes land acquisition cost.