The Andhra Pradesh government has
reportedly agreed to bring into force the escrow cover for some IPP projects
prior to their commencing commercial operations.
The projects have not been able to tie-up
funds, since the state administration had so far been reluctant to provide
upfront escrow, a precondition put forth by financial institutions for funding
the projects.
The state government has reportedly
agreed to effect the escrow cover 30-60 days prior to a project’s starting
commercial operations.
The Centre has been trying to
expedite the financial closures of these independent power projects (IPPs),
which are expected to be very cost competitive.
The projects, including the 520 MW
Ramagundam project of the BPL group (Rs 2,776 crore), the 468 MW Vemagiri
project of the Ispat Power group (Rs 1,700 crore) and the 210 MW BSES-promoted
power project, the 350 MW
Kondapally project (Rs 1,100 crore) promoted by Lanco Industries and the 464 MW
NCC/Gautami project.