Illustrative image – not actual.Another 500 MW has been added to Damodar Valley Corporation’s (DVC’s) Bokaro Thermal Power Station (BTPS).
The newly set up facility has completed a successful trial run of 72 hours and is waiting for clearance from the company to begin power generation.
The plant is presently generating 630 MW of power from its three units of 210 MW each. The power generation capacity will be raised to 1,130 MW following the operation of this unit. It will be the biggest power producer facility in the state.
Bharat Heavy Electrical (BHEL) has built the new facility at a cost of about Rs 3,000 crore.
The newly set up facility has completed a successful trial run of 72 hours and is waiting for clearance from the company to begin power generation.
The plant is presently generating 630 MW of power from its three units of 210 MW each. The power generation capacity will be raised to 1,130 MW following the operation of this unit. It will be the biggest power producer facility in the state.
Bharat Heavy Electrical (BHEL) has built the new facility at a cost of about Rs 3,000 crore.