Illustrative image – not actual.Anil Sponge has changed its project location from Raigarh to Bilaspur , following delay in receiving approval from the state government for setting up integrated steel project in Chhattisgarh.
The company is in the process of identifying land at Bilaspur and the proposal has been sent to state government for further approval. The capacity of the project might change on availability of land.
The Rs.209 crore project envisages
setting up of integrated steel plant in three phases:
|
Phases |
Facilities |
Cost (Rs.crore) |
|
I |
Re-rolling mill & steel ingots with a capacity of 50,000 tpa each and 8 MW captive power plant |
109 |
|
II |
Steel melting shops, sponge iron |
50 |
|
III |
Expansion of sponge iron |
50 |